What is the Gravity Pipeline Project?
The Gravity Pipeline (GP) Project consists of the design, construction, permitting, start-up, commissioning, and closeout of approximately 17,600 feet of wastewater gravity FRP pipe inside a concrete-segment tunnel. The work includs three shafts and will interface directly with the Front of Plant (FoP) Project at the Receiving Lift Station (RLS). Work is being implemented under a Progressive Design-Build procurement process.
What's Happening
Gravity Pipeline Project
Last Updated May 2022
Following installation of the fiberglass reinforced polymer (FRP) pipe inside the gravity tunnel, SVCW’s contractor partner for the Gravity Pipeline project, Barnard Bessac Joint Venture (BBJV), has completed installation of the last set of connection pipe segments inside the Airport Access Shaft (AAS). These pipes connect Tunnel Drive 1 to Tunnel Drive 2, and mark the successful completion to the construction of the conveyance portion of the Gravity Tunnel Project. BBJV also performed inspection walks in the tunnel to inspect the finished pipes. The Airport Access Shaft has now been prepared for backfill, with the crew all set to place backfill to support and protect the completed pipe in the shaft, followed by backfill of the Airport Access shaft to match the existing ground surface elevation.
Construction work also progresses on schedule at the San Carlos Pump Station (SCPS) site. BBJV has completed installation of the new drop structure that connects Belmont and San Carlos collection systems to the gravity tunnel. The shaft wall section has been prepared in a way that provides an inlet for new piping to carry collection system flows into the new drop structure, and into the gravity tunnel. Current work includes placement of the Fiberglass Reinforced Polymer drop structure and backfill of the shaft to grade to support the drop structure in the shaft. Completing the backfill operation will be the final step in the shaft construction for the gravity tunnel connection at San Carlos. The Bair Island shaft has been completed with the installation of the Bair Island Drop Structure, following backfilling of the shaft and removal of sheet piles that supported the shaft during construction. BBJV continues to maintain consistent coordination with its subcontractors and inspectors on each site, to ensure crew safety.
As the Gravity Pipeline project is in its last phase of work, with backfill of the AAS and installation of the drop structure to connect flows from Belmont and San Carlos, SVCW and BBJV are working together to coordinate for the startup of the system. Over at Front of Plant, the break-in site for Salus, the tunnel boring machine (TBM) that mined the 3.5-mile long tunnel, was dismantled and demobilized from the RESCU program in Fall of 2021. Looking at how far the project has come, with final site restoration beginning this month, the Gravity Pipeline project team continues working towards a safe and successful startup of the project.
AAS shaft pipe installation
AAS shaft completed pipe
Drop structure being placed in shaft at San Carlos connection to the gravity tunnel
Bair Island Drop Structure air inlet lamination
Latest Updates
Gravity Pipeline Project
Gravity Pipeline January 2022
SVCW’s contractor partner for GP, Barnard Bessac Joint Venture (BBJV), continues with the installation of the fiberglass reinforce polymer (FRP) pipe inside
Gravity Pipeline December 2021
SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), completed the downstream stage of installation of Fiber Reinforced Polymer (FRP) pipe segments in
Gravity Pipeline November 2021
SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), is proceeding with the installation of Fiber Reinforced Polymer (FRP) pipe in the
Gravity Pipeline October 2021
SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), has removed all the Tunnel Boring Machine (TBM) components and its support equipment
Quick Links
Contact
If you have questions about the Gravity Pipeline project.
- gravitypipeline@svcw.org
- 650-670-8954
Related Pages
Planning Reports
- Gravity Pipeline Project Planning Reports (Coming Soon)