What is the Front of Plant Project?
The Front of Plant (FoP) Project consists of the design, construction, permitting, start-up, commissioning, and closeout for the Receiving Lift Station (RLS), Headworks Facility, Odor Control Facilities, Influent Connector Pipe, Chemical Offload Facilities, Civil site work, Emergency Overflow pipe to storage basin and related process support systems. A Progressive Design-Build procurement process guides the Front of Plant work in stages.
What's Happening
Front of Plant Project
Last Updated May 2024
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), heads towards completion of the Front of Plant (FoP) project. SPJV completed ongoing work on the existing 54″ force main to make it possible to repurpose the existing pipe for SVCW’s future use as a conduit for recycled water piping or similar route for other services. With this, the FoP project has reached substantial completion, which is a contractual milestone. This marks a significant milestone for the RESCU Program, SVCW, SPJV and the entire project team.
SVCW hosted the RESCU Ribbon Cutting event on May 13, 2024, at the FoP site. The Director of the USEPA Office of Wastewater Management, Andrew Sawyer and a representatives of his team traveled from Washington DC to attend, and he joined Alicia Aguirre, SVCW Commission Chair, Justin Mates, Deputy San Mateo County Executive, and Teresa Herrera, Manager of SVCW, in making remarks celebrating the achievement for SVCW and its member agencies. Members of the SVCW Commission, representatives from each SVCW member agency, the County of San Mateo, including members of the Board of Supervisors, and many of SVCW’s partners and staff attended the event.
Experience the Virtual Front of Plant Project
Latest Updates
Front of Plant Project
Front of Plant May 2024
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), heads towards completion of the Front of Plant (FoP) project. SPJV completed
Front of Plant April 2024
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), heads towards completion of the Front of Plant (FoP) project. Paving and
Front of Plant March 2024
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), continues to head towards completion of the construction work at the Front
Front of Plant February 2024
Construction work at the Front of Plant (FoP) site approaches completion. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), are
Quick Links
Icon Key
- Email Address
- Links to other pages on this website
- External Link
- Download a file