What is the Front of Plant Project?
The Front of Plant (FoP) Project consists of the design, construction, permitting, start-up, commissioning, and closeout for the Receiving Lift Station (RLS), Headworks Facility, Odor Control Facilities, Influent Connector Pipe, Chemical Offload Facilities, Civil site work, Emergency Overflow pipe to storage basin and related process support systems. A Progressive Design-Build procurement process guides the Front of Plant work in stages.
What's Happening
Front of Plant Project
Last Updated February 2024
Construction work at the Front of Plant (FoP) site approaches completion. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), are set to conclude paving across the site as part of site restoration. Installation of a 2-inch asphalt concrete (AC) top coat is currently underway over the entire FoP lot, which will serve as the final pavement layer. This will be followed by striping, which involves application of a paint layer intended to give order to the site for efficient traffic flow, designate parking, and provide safe access.
Experience the Virtual Front of Plant Project
Latest Updates
Front of Plant Project
Front of Plant February 2024
Construction work at the Front of Plant (FoP) site approaches completion. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), are
Front of Plant January 2024
Construction work at the Front of Plant (FoP) site approaches completion. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), continue
Front of Plant December 2023
Construction work at the Front of Plant (FoP) site approaches completion. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), continue
Front of Plant November 2023
Construction work at the Front of Plant (FoP) site approaches completion. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), has
Quick Links
Icon Key
- Email Address
- Links to other pages on this website
- External Link
- Download a file