What is the Front of Plant Project?

The Front of Plant (FoP) Project consists of the design, construction, permitting, start-up, commissioning, and closeout for the Receiving Lift Station (RLS), Headworks Facility, Odor Control Facilities, Influent Connector Pipe, Chemical Offload Facilities, Civil site work, Emergency Overflow pipe to storage basin and related process support systems. A Progressive Design-Build procurement process guides the Front of Plant work in stages.

What's Happening

Front of Plant Project

Last Updated January 2024

Construction work at the Front of Plant (FoP) site approaches completion. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), continue striping and paving operations across the FoP site as part of site restoration. Installation of asphalt concrete (AC) paving along the FoP South Road has been completed. Current operations include installation of a 2-inch AC top coat over the entire FoP site, which will serve as the final pavement layer. 

FoP South Road paving
Paved FoP site
SFS and RLS shafts

Experience the Virtual Front of Plant Project

Latest Updates

Front of Plant Project

Scroll to Top