What is the Front of Plant Project?

The Front of Plant (FoP) Project consists of the design, construction, permitting, start-up, commissioning, and closeout for the Receiving Lift Station (RLS), Headworks Facility, Odor Control Facilities, Influent Connector Pipe, Chemical Offload Facilities, Civil site work, Emergency Overflow pipe to storage basin and related process support systems. A Progressive Design-Build procurement process guides the Front of Plant work in stages.

What's Happening

Front of Plant Project

Last Updated October 2020

Shea Parsons Joint Venture (SPJV), our contractor partner, made great progress on the installation of precast structural concrete beams that support the top deck of the Receiving Lift Station (RLS) shaft. The beams span approximately 66 feet and are about 3 feet wide. They were installed in pairs to support both the top deck/roof and to provide additional structure support of the RLS shaft.
 
Work on the RLS roof deck continues this month with installation of structural steel supports between those precast beams and the second pass wall. Reinforcing bars and placing concrete will complete the RLS shaft roof deck.
Previous
Next

Experience the Virtual Front of Plant Project

Latest Updates

Front of Plant Project

Scroll to Top