What is the Gravity Pipeline Project?
The Gravity Pipeline (GP) Project consists of the design, construction, permitting, start-up, commissioning, and closeout of approximately 17,600 feet of wastewater gravity FRP pipe inside a concrete-segment tunnel. The work includs three shafts and will interface directly with the Front of Plant (FoP) Project at the Receiving Lift Station (RLS). Work is being implemented under a Progressive Design-Build procurement process.
What's Happening
Gravity Pipeline Project
Last Updated July 2022
SVCW’s path breaking Gravity Pipeline (GP) project is nearing final completion. SVCW’s contractor partner for the project, Bernard Bessac Joint Venture (BBJV), completed construction of the 3.3-mile gravity tunnel, which will become the main link in SVCW’s new wastewater conveyance system to carry raw wastewater from the pump stations to the Headworks facility. The tunnel was mined in two phases by ‘Salus’, the tunnel boring machine (TBM) for the project. The first phase, known as Tunnel Drive 1 (TD1), was completed in March 2020, and included tunneling the upstream reach of the sewer conveyance system, starting at the Airport Access Shaft (AAS), located at Holly St and Shoreway Road, up to the Inner Bair Island shaft, located at the north end of Inner Bair Island. During the second phase, referenced as Tunnel Drive 2 (TD2), Salus tunneled from the AAS and broke in at the SFS shaft (before the shaft was fitted out for wastewater flows) in June 2021. With the completion of tunnel construction, BBJV lined the tunnel with Fiberglass Reinforced Polymer (FRP) pipe, which will ultimately carry the wastewater to the SVCW WWTP.
Completion of the tunnel construction is significant milestone for SVCW, achieving a goal nearly 10 years in the making from planning to construction. Throughout the construction activities, BBJV and its subcontractors maintained high coordination efforts with SVCW, SPJV and SVCWs public outreach partners, and delivered the project with high quality and safety results.
SVCW and BBJV are now working together with the other RESCU project teams to coordinate startup activities for the entire rehabilitated SVCW wastewater conveyance system. The startup of the system requires additional coordination with the Front of Plant and Pump Stations Improvements projects, since all the 3 projects will function together for the complete operation of the system. Startup coordination activities will be ongoing throughout the RESCU Program through the middle of 2023.
Latest Updates
Gravity Pipeline Project
Gravity Pipeline April 2021
Salus, the Tunnel Boring Machine (TBM), just entered its last stretch of tunneling while SVCW’s contractor partner, Barnard-Bessac Joint Venture
Gravity Pipeline March 2021
Salus, the Tunnel Boring Machine, is making consistent progress tunneling towards SVCW’s Wastewater Treatment Plant on its current, second drive.
Gravity Pipeline Feburary 2021
Tunneling progress of Salus’ second drive is progressing consistently, monitored by Barnard-Bessac Joint Venture (BBJV). This month, BBJV started preparations
Gravity Pipeline January 2021
SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), continued to make significant and safe tunneling progress with Salus, the Tunnel Boring
Quick Links
Contact
If you have questions about the Gravity Pipeline project.
- gravitypipeline@svcw.org
- 650-670-8954
Related Pages
Planning Reports
- Gravity Pipeline Project Planning Reports (Coming Soon)