What is the Pump Stations Project?
All SVCW pump stations require replacement or rehabilitation. The Menlo Park Pump Station will be rehabilitated; the Redwood City Pump Station will be replaced; the Belmont Pump Station will be rehabilitated; and, the San Carlos Pump Station is no longer needed due to the new gravity pipeline. Flows from San Carlos and Belmont will enter into the gravity pipeline via a drop structure at the current San Carlos pump station site. Flows from the Menlo Park Pump Station and the Redwood City Pump Station will flow through the new 48-inch force main to a drop structure at Inner Bair Island.
What's Happening
Pump Station Improvements Project
Last Updated January 2025
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), concluded construction of the Redwood City Pump Station (RCPS) in October 2024. With the construction of the new pump station complete, a 30-day acceptance testing was undertaken. The acceptance test was performed on most of the equipment or systems to verify compliance with design criteria, and to ensure that the installation and operation met relevant codes and the design criteria established for the pump station. These tests form a critical part of the startup and commissioning process of each facility, and are the final step prior to full startup.
With the Front of Plant (FoP), Gravity Pipeline (GP), and rest of the Pump Stations Improvements (PSI) projects already complete, the end of the acceptance testing at RCPS brings the RESCU Program to a conclusion. This is a massive achievement for SVCW in executing three multi-year, progressive design-build (PDB) projects concurrently, from planning and design to construction and startup.
After 8 years of planning, design, and construction of three concurrent PDB projects, the RESCU Program’s financial performance is exceptional for a large public works project, with final costs finishing within 0.06% of the Program budget. The RESCU Program involved continuous and efficient coordination between SVCW (Owner) and its team of contractors, consultants, construction managers and stakeholders. It will ensure that SVCW and its ratepayers are served by a reliable 100-year wastewater conveyance system to continue SVCW’s mission of sustainably protecting public health and the environment.
Latest Updates
Pump Station Project
Pump Stations Improvements Update – January 2025
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), concluded construction of the Redwood City Pump Station (RCPS) in October 2024.
Pump Stations Improvements October 2024
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), approaches completion of the Redwood City Pump Station (RCPS) project. SPJV completed
Pump Stations Improvements July 2024
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), approach completion of the Belmont
Pump Stations Improvements May 2024
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), approach completion of the Belmont
Quick Links
Icon Key
- Email Address
- Links to other pages on this website
- External Link
- Download a file