What is the Pump Stations Project?

All SVCW pump stations require replacement or rehabilitation. The Menlo Park Pump Station will be rehabilitated; the Redwood City Pump Station will be replaced; the Belmont Pump Station will be rehabilitated; and, the San Carlos Pump Station is no longer needed due to the new gravity pipeline. Flows from San Carlos and Belmont will enter into the gravity pipeline via a drop structure at the current San Carlos pump station site. Flows from the Menlo Park Pump Station and the Redwood City Pump Station will flow through the new 48-inch force main to a drop structure at Inner Bair Island.

What's Happening

Pump Station Improvements Project

Last Updated May 2024

SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), approach completion of the Belmont Gravity Pipeline (BGP) project. Wastewater from the Belmont and San Carlos collection systems is now being conveyed to the San Carlos Drop Structure, from where it is transported via the new gravity tunnel to the new SVCW Headworks for treatment. At the San Carlos Pump Station (SCPS) electrical room, installation of the new motor control center (MCC) is complete, and installation of supplemental equipment continues.

PEC has concluded road restoration activities at the Bair Island and San Carlos Pump Station sites and brought the areas back to pre-construction conditions. Demolition of the existing, now decommissioned, Belmont Pump Station (BPS) is underway. Concurrently, a 30-day acceptance test of the new piping at the SCPS and the BGP takes place between mid-May and mid-June.

At the Redwood City Pump Station (RCPS) wet well and screening building, SPJV proceeds with electrical and structural improvements. At the wet well structure, SPJV completed installing discharge piping on the south side and began forming concrete for construction of the sanitary sewer force main (SSFM) supports. Cutover to the new PG&E service has been completed. Additional work at the pump station includes installation of trench drain, miscellaneous piping and appurtenances in the electrical building and site finishes.

Trench drain installation at RCPS
RCPS south side discharge piping
RCPS VFDs
SCPS Connecting Piping

Latest Updates

Pump Station Project

Quick Links

Contact

If you have questions about the Pump Station project.

Icon Key

Scroll to Top