What is the Pump Stations Project?
All SVCW pump stations require replacement or rehabilitation. The Menlo Park Pump Station will be rehabilitated; the Redwood City Pump Station will be replaced; the Belmont Pump Station will be rehabilitated; and, the San Carlos Pump Station is no longer needed due to the new gravity pipeline. Flows from San Carlos and Belmont will enter into the gravity pipeline via a drop structure at the current San Carlos pump station site. Flows from the Menlo Park Pump Station and the Redwood City Pump Station will flow through the new 48-inch force main to a drop structure at Inner Bair Island.
What's Happening
Pump Station Improvements Project
Last Updated January 2025
Latest Updates
Pump Station Project
Pump Stations Improvements December 2023
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), continues to make progress on
Pump Stations Improvements November 2023
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), have concluded restoration of jacking
Pump Stations Improvements October 2023
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), are set to complete restoration
Pump Stations Improvements September 2023
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), continue restoration of jacking and