Front of Plant March 2021
Shea Parsons Joint Venture (SPJV) is working on finishing up its installation of the Receiving Lift Station (RLS) pump discharge
Front of Plant March 2021 Read More »
Shea Parsons Joint Venture (SPJV) is working on finishing up its installation of the Receiving Lift Station (RLS) pump discharge
Front of Plant March 2021 Read More »
This month, Shea Parsons Joint Venture will install sheet piles at the Redwood City Pump Station to provide stable excavation
Pump Station Improvements March 2021 Read More »
Salus, the Tunnel Boring Machine, is making consistent progress tunneling towards SVCW’s Wastewater Treatment Plant on its current, second drive.
Gravity Pipeline March 2021 Read More »