Pump Stations Improvements August 2023
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), continue restoration of jacking and
Pump Stations Improvements August 2023 Read More »
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), and SPJV’s subcontractor Power Engineering Construction (PEC), continue restoration of jacking and
Pump Stations Improvements August 2023 Read More »
Construction work at the Front of Plant (FoP) site approaches completion. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), continues