Gravity Pipeline March 2021
Salus, the Tunnel Boring Machine, is making consistent progress tunneling towards SVCW’s Wastewater Treatment Plant on its current, second drive. …
All updates related to the Gravity Pipeline project.
Salus, the Tunnel Boring Machine, is making consistent progress tunneling towards SVCW’s Wastewater Treatment Plant on its current, second drive. …
Tunneling progress of Salus’ second drive is progressing consistently, monitored by Barnard-Bessac Joint Venture (BBJV). This month, BBJV started preparations …
SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), continued to make significant and safe tunneling progress with Salus, the Tunnel Boring …
Today, the U.S. Environmental Protection Agency (EPA) announced that after a robust review process, the WIFIA Selection Committee chose two …
Gravity Pipeline Connection System SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), installed the excavation support system, or secant piles, for …
Salus, the Tunnel Boring Machine (TBM), is already on its second drive of mining, making its way towards SVCW’s wastewater …
Salus began continuous mining from the launch shaft towards the SVCW plant after a planned stoppage. During the final stop, …
After a successful first tunnel drive, Salus, the Tunnel Boring Machine, is ready for her next journey – tackling twice …
Salus, the Tunnel Boring Machine (TBM), safely began her second drive from the launch shaft to SVCW’s wastewater treatment facility …
After Salus completed its first drive late-March, the Barnard-Bessac Joint Venture (BBJV) crew began disassembling the Tunnel Boring Machine (TBM) …