Front of Plant July 2021
Construction work at the Headworks Facility and Receiving Lift Station (RLS) are ongoing, with SVCW’s contractor partner, Shea Parsons Joint
Front of Plant July 2021 Read More »
Construction work at the Headworks Facility and Receiving Lift Station (RLS) are ongoing, with SVCW’s contractor partner, Shea Parsons Joint
Front of Plant July 2021 Read More »
Construction work is proceeding at the Redwood City Pump Station. SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), is continuing
Pump Station Improvements July 2021 Read More »
Another Month of Good News! Salus, the mighty tunnel boring machine (TBM), has successfully completed its second tunneling drive and
Gravity Pipeline July 2021 Read More »