Pump Stations April 2021

SPJV recently completed the electrical building foundation at the new Redwood City Pump Station (RWCPS). This month, SPJV will install rebar and pour concrete for the building while concurrently constructing a foundation slab nearby for the standby generator.
SPJV is also coordinating with PG&E to relocate existing overhead power lines adjacent to the RWCPS site and run as underground conduits.
 
Meanwhile, construction of the Belmont Gravity Pipeline is underway. This team is using a series of shafts and micro tunneling operations to install a gravity pipeline that will replace the Belmont Pump Station. Next month they will start construction on three of the eight shafts.