SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), is making good progress with construction at the Redwood City Pump Station (RCPS). The electrical building walls are being constructed, with electrical conduits being installed under the building slab. SPJV will also be excavating the wet well and building the screening this month.
Work on the Belmont Gravity pipeline is ongoing along Shoreway Road. This month, ground improvement and excavation of three shafts will be carried out to prepare for the micro-tunneling operations for the Belmont gravity pipeline construction. Since the construction work impacts the public, SVCW is providing regular construction updates and has open communications with the cities of San Carlos and Belmont, and with the businesses in the area.
Go here for more about the Pump Station Improvements project.