Front of Plant November 2022
Construction work progresses at the Receiving Lift Station (RLS) at the Front of Plant (FoP) site. SVCW’s contractor partner, Shea […]
Front of Plant November 2022 Read More »
All general RESCU program updates not specific to one of its sub-projects.
Construction work progresses at the Receiving Lift Station (RLS) at the Front of Plant (FoP) site. SVCW’s contractor partner, Shea […]
Front of Plant November 2022 Read More »
Construction work on the Belmont Gravity Pipeline (BGP) along Shoreway Road in Belmont and San Carlos continues. SVCW’s contractor partner,
Pump Stations Improvements November 2021 Read More »
SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), is proceeding with the installation of Fiber Reinforced Polymer (FRP) pipe in the
Gravity Pipeline November 2021 Read More »
At the Front of Plant site, SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), is actively working in the two
Front of Plant November 2021 Read More »
Silicon Valley Clean Water (SVCW)’s contractor partner, Shea Parsons Joint Venture (SPJV), is making consistent progress on the Belmont Gravity
Pump Station Improvements September 2021 Read More »
Silicon Valley Clean Water (SVCW)’s contractor partner, Barnard-Bessac Joint Venture (BBJV), is finishing up work at the Surge and Flow
Gravity Pipeline September 2021 Read More »
Silicon Valley Clean Water’s contractor partner, Shea Parsons Joint Venture (SPJV) is continuing work within the Receiving Lift Station (RLS).
Front of Plant September 2021 Read More »
Today, the U.S. Environmental Protection Agency (EPA) announced that after a robust review process, the WIFIA Selection Committee chose two
The Pump Station Improvement (PSI) project is in the final stages of design work. Crews are preparing to mobilize to
Pump Station Improvement Project October 2020 Read More »
Salus began continuous mining from the launch shaft towards the SVCW plant after a planned stoppage. During the final stop,
Gravity Pipeline October 2020 Read More »