Front of Plant April 2020 Update

Front of Plant

In May, construction at the Front of Plant includes building the interior shaft walls for the receiving lift station (RLS) with rebar paneling. Shea-Parsons Joint Venture constructed the vertical shaft by installing support of excavation (SoE) as a method to support the surrounding soil, facilitating a safe and efficient work space for construction of the shaft. Second pass wall is an interior wall constructed immediately inside the SoE wall and is a part of the structural support for the shaft. The second pass wall will be the visible wall surface within the RLS shaft.

Receiving Lift Station Vertical Shaft
Scroll to Top