Front of Plant February 2021

In February, SVCW’s contractor partner Shea Parsons Joint Venture (SPJV) is proceeding with architectural work at the Headworks Facility. This includes installing permanent stairs and handrails for accessibilty, and completing the roofing of the electrical building.
SPVJ continues work on the Receiving Lift Station (RLS) vertical shaft. SPJV started installing pipe supports on the shaft walls that will secure the RLS pump discharge pipes and the shaft sump pump discharge pipe. The discharge pipes will be routed from the RLS pump discharge vertically, up the RLS shaft wall to ground surface elevation, where the pipes will exit the RLS shaft through a custom designed opening in the shaft wall. From this opening, the discharge pipes will extend to the new Headworks Facility to deliver wastewater to the channels that carry the flow to the new automated bar screens.
For more information about the Front of Plant project, go here.