Pump Station Improvements May 2020

Belmont Gravity Pipeline

At its April meeting, the SVCW Commission authorized part two of the PSI project, the Belmont Gravity Pipeline. Shea-Parsons Joint Venture (SPJV) can now proceed with construction work, including constructing the pipeline itself. SPJV will coordinate the startup of the new facilities that will deliver raw wastewater from the SVCW member agencies to the wastewater treatment plant.

Redwood City Pump Station

The 60% design is being finalized as the second round of flow modeling scenarios by Clemson Laboratory culminates. Once complete, SVCW and SPJV will be able to come to an agreement for the estimated cost of building the new Redwood City Pump station. The SVCW Commission will then be able to consider approving the next phase: construction.