Front of Plant December 2020
In December 2020, the Front of Plant (FoP) team will be completing installation of the 63-inch High Density Polyethylene (HDPE) […]
Front of Plant December 2020 Read More »
In December 2020, the Front of Plant (FoP) team will be completing installation of the 63-inch High Density Polyethylene (HDPE) […]
Front of Plant December 2020 Read More »
The Pump Stations Improvement (PSI) project is in the process of transitioning from the design phase to its construction phase.
Pump Station Improvements November 2020 Update Read More »
Salus, the Tunnel Boring Machine (TBM), is already on its second drive of mining, making its way towards SVCW’s wastewater
Gravity Pipeline Update November 2020 Read More »
Work on the roof deck for the Receiving Lift Station (RLS) shaft continues this month. Shea Parsons Joint Venture (SPJV),
November 2020 Front of Plant Update Read More »
The Pump Station Improvement (PSI) project is in the final stages of design work. Crews are preparing to mobilize to
Pump Station Improvement Project October 2020 Read More »
Salus began continuous mining from the launch shaft towards the SVCW plant after a planned stoppage. During the final stop,
Gravity Pipeline October 2020 Read More »
Shea Parsons Joint Venture (SPJV), our contractor partner, made great progress on the installation of precast structural concrete beams that
Front of Plant October 2020 Read More »
Receiving Lift Station This month, construction of the second pass walls continues within the Receiving Lift Station (RLS) vertical shaft.
Front of Plant August 2020 Read More »
This month, work will progress to 100% on the design elements for three parts of the Pump Station Improvements (PSI)
Pump Station Improvement Update August 2020 Read More »
After a successful first tunnel drive, Salus, the Tunnel Boring Machine, is ready for her next journey – tackling twice
Tunnel Boring Machine Begins Second Drive Read More »