Front of Plant January 2021
This project recently reached a major milestone–the completion of all above ground walls and concrete structures. SVCW’s contractor partner, Shea […]
Front of Plant January 2021 Read More »
This project recently reached a major milestone–the completion of all above ground walls and concrete structures. SVCW’s contractor partner, Shea […]
Front of Plant January 2021 Read More »
SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), continued to make significant and safe tunneling progress with Salus, the Tunnel Boring
Gravity Pipeline January 2021 Read More »
Today, the U.S. Environmental Protection Agency (EPA) announced that after a robust review process, the WIFIA Selection Committee chose two
Redwood City Pump Station Preliminary work including mobilization to the Redwood City Pump Station (RCPS) site and initial preparations for
Pump Station Improvements December 2020 Read More »
Gravity Pipeline Connection System SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), installed the excavation support system, or secant piles, for
Gravity Pipeline December 2020 Read More »
In December 2020, the Front of Plant (FoP) team will be completing installation of the 63-inch High Density Polyethylene (HDPE)
Front of Plant December 2020 Read More »
The Pump Stations Improvement (PSI) project is in the process of transitioning from the design phase to its construction phase.
Pump Station Improvements November 2020 Update Read More »
Salus, the Tunnel Boring Machine (TBM), is already on its second drive of mining, making its way towards SVCW’s wastewater
Gravity Pipeline Update November 2020 Read More »
Work on the roof deck for the Receiving Lift Station (RLS) shaft continues this month. Shea Parsons Joint Venture (SPJV),
November 2020 Front of Plant Update Read More »
The Pump Station Improvement (PSI) project is in the final stages of design work. Crews are preparing to mobilize to
Pump Station Improvement Project October 2020 Read More »