Gravity Pipeline May 2021
Salus is in its last stretch of tunneling! Barnard-Bessac Joint Venture (BBJV) has consistently monitored and maintained the tunneling equipment …
Salus is in its last stretch of tunneling! Barnard-Bessac Joint Venture (BBJV) has consistently monitored and maintained the tunneling equipment …
In May, the grit washer classifiers were installed at the Headworks facility. Wastewater passes through the grit removal system then …
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), is making good progress with construction at the Redwood City Pump Station …
Shea Parsons Joint Venture (SPJV) is working on finishing up its installation of the Receiving Lift Station (RLS) pump discharge …
This month, Shea Parsons Joint Venture will install sheet piles at the Redwood City Pump Station to provide stable excavation …
Salus, the Tunnel Boring Machine, is making consistent progress tunneling towards SVCW’s Wastewater Treatment Plant on its current, second drive. …
Tunneling progress of Salus’ second drive is progressing consistently, monitored by Barnard-Bessac Joint Venture (BBJV). This month, BBJV started preparations …
In February, SVCW’s contractor partner Shea Parsons Joint Venture (SPJV) is proceeding with architectural work at the Headworks Facility. This …
This month SPJV continues to carry out preliminary work near the San Carlos Pump Station, and is in the process …
SPJV continues to carry out preliminary work near the San Carlos Pump Station, which includes moving into their laydown areas. …