Gravity Pipeline February 2022
SVCW’s contractor partner for the Gravity Pipeline project, Barnard BessacJoint Venture (BBJV), continues with the installation of the fiberglass reinforced polymer …
SVCW’s contractor partner for the Gravity Pipeline project, Barnard BessacJoint Venture (BBJV), continues with the installation of the fiberglass reinforced polymer …
At the Front of Plant site, SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), has completed work on the manifold …
Construction work on the Belmont Gravity Pipeline (BGP) along Shoreway Road in Belmont and San Carlos continues. Following the completion …
SVCW’s contractor partner for GP, Barnard Bessac Joint Venture (BBJV), continues with the installation of the fiberglass reinforce polymer (FRP) pipe inside …
At the Front of Plant site, SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), has completed work on the connection …
Construction work continues on the Belmont Gravity Pipeline (BGP) along Shoreway Road in Belmont and San Carlos. SVCW’s contractor partner, …
SVCW’s contractor partner, Barnard-Bessac Joint Venture (BBJV), completed the downstream stage of installation of Fiber Reinforced Polymer (FRP) pipe segments in …
This month at the Front of Plant site, SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), started working on the …
After nearly two years of construction, Silicon Valley Clean Water’s (SVCW) long-anticipated Gravity Pipeline project successfully achieved a major milestone …
Construction work on the Belmont Gravity Pipeline (BGP) along Shoreway Road in Belmont and San Carlos continues. SVCW’s contractor partner, …