Front of Plant Status November 9, 2017
Progressive Design-Build – Status of Selection Process On November 9, 2017 the SVCW Commission approved a Design-Build agreement with JF […]
Front of Plant Status November 9, 2017 Read More »
Progressive Design-Build – Status of Selection Process On November 9, 2017 the SVCW Commission approved a Design-Build agreement with JF […]
Front of Plant Status November 9, 2017 Read More »
Silicon Valley Clean Water’s Front of the Plant project at 1400 Radio Road, Redwood City, advanced Thursday (November 9) when
SVCW Front of Plant Project Advances with Approval for Design-Build Joint Venture Read More »
Progressive Design-Build – Status of Selection Process On October 11, 2017 the SVCW Commission approved a Design-Build agreement with the
Gravity Pipeline Status October 11, 2017 Read More »
Silicon Valley Clean Water sent out notice to residents of increased truck traffic along Redwood Shores Parkway through September 20.
Update on SVCW Front of Plant Work and Truck Activity Read More »
The Silicon Valley Clean Water (SVCW) Commission Thursday (October 5, 2017) approved a design-build agreement which will advance the gravity
SVCW Commission Actions Advance Gravity Pipeline Project, Update CIP Spending Read More »
Truck traffic along Redwood Shores Parkway will be greater than anticipated for approximately a four-week period starting this week. The
Truck Traffic to Increase Through September 20 Along Redwood Shores Parkway Read More »
The FoP project heavy construction will begin on Monday July 31and last about three weeks. Additional bulldozers, earthmovers, dump trucks,
Site preparation improvements are underway at Silicon Valley Clean Water’s 10-acre front-of-plant (FoP) site at 1400 Radio Road at the
Front of Plant Site Preparation Work Underway at Silicon Valley Clean Water Read More »
The Silicon Valley Clean Water (SVCW) Commission on Thursday, April 13, approved the Regional Environmental Sewer Conveyance Upgrade (RESCU) Program,
SVCW has completed the EIR for the Wastewater Conveyance System and Treatment Plant Reliability Improvement Project. The EIR was certified