Pump Stations April 2021
SPJV recently completed the electrical building foundation at the new Redwood City Pump Station (RWCPS). This month, SPJV will install …
SPJV recently completed the electrical building foundation at the new Redwood City Pump Station (RWCPS). This month, SPJV will install …
Salus, the Tunnel Boring Machine (TBM), just entered its last stretch of tunneling while SVCW’s contractor partner, Barnard-Bessac Joint Venture …
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), who has been working within the Receiving Lift Station (RLS) shaft over …
The Pump Station Improvements (PSI) team continues to review the design for the Menlo Park Pump Station rehabilitation. Shea-Parsons Joint …
Salus, the Tunnel Boring Machine (TBM), arrived at its first destination at the shaft located on the northern end of …
Front of Plant work continues to progress. SVCW’s design-build partner, Shea-Parsons Joint Venture (SPJV), imprinted the SVCW logo onto the …
As part of the RESCU Program, SVCW has ongoing work at the corner of Shoreway Road and Holly Street. A …
Design development for the Pump Station Improvement (PSI) project is nearing a significant milestone in December. SVCW’s design build partner …
The first stage of Salus’ assembly in the tunnel was completed last month by SVCW’s tunnel contractor partner, Barnard-Bessac Joint …
Design for the Front of Plant (FoP) project is on track, with the 100% design package being completed this month. …