Pump Stations Improvements Update – January 2025
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), concluded construction of the Redwood City Pump Station (RCPS) in October 2024.
Pump Stations Improvements Update – January 2025 Read More »
SVCW’s Design Builder, Shea Parsons Joint Venture (SPJV), concluded construction of the Redwood City Pump Station (RCPS) in October 2024.
Pump Stations Improvements Update – January 2025 Read More »
We are thrilled to share that the Gravity Pipeline Project was recently featured in Arup Journal! The article entitled, “Wastewater
Construction work continues on the Belmont Gravity Pipeline (BGP) along Shoreway Road in Belmont and San Carlos. SVCW’s contractor partner,
Pump Stations Improvements Read More »
Following installation of the fiberglass reinforced polymer (FRP) pipe inside the gravity tunnel, SVCW’s contractor partner for the Gravity Pipeline
Gravity Pipeline April 2022 Read More »
At the Front of Plant site, SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), continues to make progress at the
Front of Plant April 2022 Read More »
Construction work advances as scheduled on the Belmont Gravity Pipeline (BGP) along Shoreway Road in Belmont and San Carlos. SVCW’s
Pump Stations Improvements March 2022 Read More »
SVCW’s contractor partner for the Gravity Pipeline project, Barnard Bessac Joint Venture (BBJV), has completed installation of the fiberglass reinforced
Gravity Pipeline March 2022 Read More »
At the Front of Plant site, SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), continues to make progress at the
Front of Plant March 2022 Read More »
Construction work progresses on the Belmont Gravity Pipeline (BGP) along Shoreway Road in Belmont and San Carlos. SVCW’s contractor partner,
Pump Stations Improvements February 2022 Read More »
SVCW’s contractor partner for the Gravity Pipeline project, Barnard BessacJoint Venture (BBJV), continues with the installation of the fiberglass reinforced polymer
Gravity Pipeline February 2022 Read More »