Front of Plant October 2021
Construction work within the Receiving Lift Station (RLS) at the Front of Plant site continues to progress. SVCW’s contractor partner, […]
Front of Plant October 2021 Read More »
All updates related to the Front of Plant project.
Construction work within the Receiving Lift Station (RLS) at the Front of Plant site continues to progress. SVCW’s contractor partner, […]
Front of Plant October 2021 Read More »
Silicon Valley Clean Water’s contractor partner, Shea Parsons Joint Venture (SPJV) is continuing work within the Receiving Lift Station (RLS).
Front of Plant September 2021 Read More »
At the Front of Plant, construction work within the Receiving Lift Station (RLS) shaft and Headworks Facility is progressing on
Front of Plant August 2021 Read More »
Construction work at the Headworks Facility and Receiving Lift Station (RLS) are ongoing, with SVCW’s contractor partner, Shea Parsons Joint
Front of Plant July 2021 Read More »
Silicon Valley Clean Water (SVCW)’s contractor partner, Shea Parsons Joint Venture (SPJV), continues working on the Headworks Facility at the
Front of Plant June 2021 Read More »
In May, the grit washer classifiers were installed at the Headworks facility. Wastewater passes through the grit removal system then
Front of Plant May 2021 Read More »
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), who has been working within the Receiving Lift Station (RLS) shaft over
Front of Plant April 2021 Read More »
Shea Parsons Joint Venture (SPJV) is working on finishing up its installation of the Receiving Lift Station (RLS) pump discharge
Front of Plant March 2021 Read More »
In February, SVCW’s contractor partner Shea Parsons Joint Venture (SPJV) is proceeding with architectural work at the Headworks Facility. This
Front of Plant February 2021 Read More »
This project recently reached a major milestone–the completion of all above ground walls and concrete structures. SVCW’s contractor partner, Shea
Front of Plant January 2021 Read More »