Tunnel Boring Machine Begins Second Drive
After a successful first tunnel drive, Salus, the Tunnel Boring Machine, is ready for her next journey – tackling twice […]
Tunnel Boring Machine Begins Second Drive Read More »
After a successful first tunnel drive, Salus, the Tunnel Boring Machine, is ready for her next journey – tackling twice […]
Tunnel Boring Machine Begins Second Drive Read More »
Belmont Gravity Pipeline The Belmont Gravity Pipeline will replace the existing pumps and force main, which carries wastewater from the
Pump Station Improvements July 2020 Read More »
Salus, the Tunnel Boring Machine (TBM), safely began her second drive from the launch shaft to SVCW’s wastewater treatment facility
Gravity Pipeline July 2020 Read More »
Receiving Lift Station Shea Parson Joint Venture (SPJV) is completing the construction of the second pass walls in the Receiving
Front of Plant July 2020 Read More »
Belmont Gravity Pipeline At its April meeting, the SVCW Commission authorized part two of the PSI project, the Belmont Gravity
Pump Station Improvements May 2020 Read More »
After Salus completed its first drive late-March, the Barnard-Bessac Joint Venture (BBJV) crew began disassembling the Tunnel Boring Machine (TBM)
Gravity Pipeline May 2020 Read More »
Construction of the second pass walls continues at the Front of Plant receiving lift station (RLS). Shea-Parsons Joint Venture constructed
Front of Plant May 2020 Update Read More »
Front of Plant In May, construction at the Front of Plant includes building the interior shaft walls for the receiving
Front of Plant April 2020 Update Read More »
Pump Station Improvements Menlo Park Pump Station At its March meeting, the SVCW Commission authorized the first part of construction
Pump Station Update Read More »
Gravity Pipeline A bright note during an otherwise gloomy time, Salus, the Tunnel Boring Machine (TBM), completed her first tunnel
Gravity Pipeline Update Read More »