Gravity Pipeline May 2021
Salus is in its last stretch of tunneling! Barnard-Bessac Joint Venture (BBJV) has consistently monitored and maintained the tunneling equipment […]
Gravity Pipeline May 2021 Read More »
Salus is in its last stretch of tunneling! Barnard-Bessac Joint Venture (BBJV) has consistently monitored and maintained the tunneling equipment […]
Gravity Pipeline May 2021 Read More »
In May, the grit washer classifiers were installed at the Headworks facility. Wastewater passes through the grit removal system then
Front of Plant May 2021 Read More »
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), is making good progress with construction at the Redwood City Pump Station
Pump Station Improvements May 2021 Read More »
Shea Parsons Joint Venture (SPJV) is working on finishing up its installation of the Receiving Lift Station (RLS) pump discharge
Front of Plant March 2021 Read More »
This month, Shea Parsons Joint Venture will install sheet piles at the Redwood City Pump Station to provide stable excavation
Pump Station Improvements March 2021 Read More »
Salus, the Tunnel Boring Machine, is making consistent progress tunneling towards SVCW’s Wastewater Treatment Plant on its current, second drive.
Gravity Pipeline March 2021 Read More »
Tunneling progress of Salus’ second drive is progressing consistently, monitored by Barnard-Bessac Joint Venture (BBJV). This month, BBJV started preparations
Gravity Pipeline Feburary 2021 Read More »
In February, SVCW’s contractor partner Shea Parsons Joint Venture (SPJV) is proceeding with architectural work at the Headworks Facility. This
Front of Plant February 2021 Read More »
This month SPJV continues to carry out preliminary work near the San Carlos Pump Station, and is in the process
Pump Station Improvements February 2021 Read More »
SPJV continues to carry out preliminary work near the San Carlos Pump Station, which includes moving into their laydown areas.
Pump Station Improvements January 2021 Read More »