Front of Plant June 2021
Silicon Valley Clean Water (SVCW)’s contractor partner, Shea Parsons Joint Venture (SPJV), continues working on the Headworks Facility at the […]
Front of Plant June 2021 Read More »
Silicon Valley Clean Water (SVCW)’s contractor partner, Shea Parsons Joint Venture (SPJV), continues working on the Headworks Facility at the […]
Front of Plant June 2021 Read More »
Good news! Salus, the mighty tunnel boring machine, has broken through the shaft! Having tunneled nearly 13,000 feet from its
Gravity Pipeline June 2021 Read More »
Salus is in its last stretch of tunneling! Barnard-Bessac Joint Venture (BBJV) has consistently monitored and maintained the tunneling equipment
Gravity Pipeline May 2021 Read More »
In May, the grit washer classifiers were installed at the Headworks facility. Wastewater passes through the grit removal system then
Front of Plant May 2021 Read More »
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), is making good progress with construction at the Redwood City Pump Station
Pump Station Improvements May 2021 Read More »
SPJV recently completed the electrical building foundation at the new Redwood City Pump Station (RWCPS). This month, SPJV will install
Pump Stations April 2021 Read More »
Salus, the Tunnel Boring Machine (TBM), just entered its last stretch of tunneling while SVCW’s contractor partner, Barnard-Bessac Joint Venture
Gravity Pipeline April 2021 Read More »
SVCW’s contractor partner, Shea Parsons Joint Venture (SPJV), who has been working within the Receiving Lift Station (RLS) shaft over
Front of Plant April 2021 Read More »
Shea Parsons Joint Venture (SPJV) is working on finishing up its installation of the Receiving Lift Station (RLS) pump discharge
Front of Plant March 2021 Read More »
This month, Shea Parsons Joint Venture will install sheet piles at the Redwood City Pump Station to provide stable excavation
Pump Station Improvements March 2021 Read More »